Crude Pipeline

EPIC CRUDE PIPELINE

The EPIC Crude Oil Pipeline will extend from Orla, Texas to the Port of Corpus Christi, Texas. The project includes terminals in Orla, Pecos, Saragosa, Crane, Wink, Midland, Helena and Gardendale, with Port of Corpus Christi connectivity and export access. It will service the Delaware, Midland and Eagle Ford Basins. Right of way is 100 percent secured for the first two phases of the system.

Construction of the 30” Crude Oil Pipeline is well underway, with a current overall completion rate of over 50%. The project remains on budget and the mainline is expected to be complete in January 2020. The Crude Oil Pipeline will have an initial capacity of 600,000 barrels of oil per day, with throughput anticipated to begin ramping up during the first quarter of 2020.

To obtain an overview of our pipeline, please click here to download the map of our system.

Subscribe to receive Tariff Notifications by clicking here.